D Block update

D Block update

Author: Marketing Department

Installation of the glass skylights is scheduled for this week. Brickwork is continuing on the street-side facade and sections of external scaffolding are starting to be removed.

Installation of the terrazzo tiling to the dining hall area has commenced, with joinery and stainless steel nearing completion to the kitchen and servery counter.

Services fit off continues to the classrooms, with the installation of AV equipment and carpet scheduled to commence later this week.